A. Histograms
B. Explain Plan
C. Resource Plan
D. Resource User Group
E. Resource Consumer Group
F. Resource Plan Directives
G. Resource Plan Assignments
Answer: C, E, F
Explanation:
Resource Plan, Resource Consumer Group and Resource Plan Directives are used when administering systems with the database Resource Manager.
Incorrect Answers
A: Histograms are not used with the database Resource Manager.
B: Explain Plan has no relation with the database Resource Manager.
D: There is Resource Consumer Group, not Resource User Group in Resource Manager.
G: There is no Resource Plan Assignments for Resource Manager.
OCP: Oracle 9i Performance Tuning Study Guide, Jaseph C. Johnson, p. 517-547
Chapter 10: Operating System Tuning