Before you can create a resource plan directive, which of the following steps must you complete? (Choose two.)
A. Create a resource plan.
B . Specify which plan will be used by the instance.
C. Create a pending area.
D . Validate the resource plan.
E . Submit the resource plan.
Explanation:
Answer A and C: If you want to create a resource plan directive, you must first create a resource plan and resource consumer groups. Before you can create a resource plan, you must create a pending area. Validate and submit a resource plan after you create the resource plan directives. Once the plan has been submitted, you can specify that the plan will be used by the instance.